Traffic Updates

Riverwoods Dr and SB Heidenreich to open Sept 23, weather permitting

 

The Hall Road M-59 construction project will last for two years:

Phase I: March-December 2021

Phase II: March-December 2022

Two lanes will stay open in each direction 7:00 am to 7:00 pm daily

Traffic may be reduced to one lane in each direction during off-peak hours

Work will occur day and night.

Traffic Flow Staging

Stage I: Traffic flows in right and center lanes

m-59-construction-stage-1

Stage II: Traffic shifts to left and center lanes

m-59-construction-stage-2

Stage III: Traffic shifts to right and center lanes

m-59-construction-stage-3