Traffic Updates
The Hall Road M-59 construction project will last for two years:
- Phase I: March-December 2021
- Phase II: March-December 2022
- Two lanes will stay open in each direction 7:00 am to 7:00 pm daily
- Traffic may be reduced to one lane in each direction during off-peak hours
- Work will occur day and night
Traffic Flow Staging
Stage I: Traffic flows in right and center lanes

Stage II: Traffic shifts to left and center lanes

Stage III: Traffic shifts to right and center lanes